City of Hampton, Virginia
Resolution
|
22 Lincoln Street
Hampton, VA 23669
www.hampton.gov
|
|
File
Number: 05-0748
|
|
Enactment Number: -
|
|
|
|
|
|
Cmdr. Shepard Boulevard Extension
RESOLUTION
RESOLUTION
A resolution
appropriating $1.2 million from the VDOT Urban Construction Revenue
Account/Capital Projects Fund for anticipated expenses related to the Cmdr. Shepard Boulevard project
WHEREAS, additional expenses of $1.2
million are anticipated for the Cmdr. Shepard Boulevard project prior to
construction of the roadway; and
WHEREAS,
$650,000 of this amount is the estimated cost of acquiring the remaining
parcels within Phase 1 of the project; and
WHEREAS,
$400,000 of this amount is necessary for the construction of the intersection
of North Campus Parkway and future Cmdr. Shepard Boulevard Extension and these
funds are expected to be reimbursed to the City by VDOT under the VDOT Revenue
Sharing program; and
WHEREAS,
$100,000 of this amount is needed for additional consultant services to
complete the Corps requirements for the mitigation plan; and
WHEREAS,
$50,000 of this amount is needed for legal counsel support in negotiating with
the Corps of Engineers and Department of Environmental Quality on the approval
of the mitigation plan, and on other matters pertaining to environmental
permitting.
NOW, THEREFORE,
BE IT RESOLVED that $1.2 million is hereby appropriated from the VDOT Urban
Construction Revenue Account/Capital Projects Fund for anticipated expenses
relating to Cmdr. Shepard Boulevard, Phase 1.
Adopted at
the regular meeting of the City Council of the City of Hampton, Virginia, held
on December 14, 2006.
Signed by ____________________________ Date
_________________
Ross A. Kearney, II, Mayor
Attested by ____________________________ Date _________________
Katherine K. Glass
Clerk of the Council