Legislation # 06-0370 Enactment Number none
Type Resolution Effective Date none
Introduction Date 6/14/2006
Title Resolution Approving the Location and Major Design Features of the Big Bethel Road / Roberta Drive Intersection Improvements Project and the Big Bethel Road / Joynes Road Intersection Improvements Project. Engineering Services Project Numbers 04-001 and 05-007.
 
Legislation History 06-0370
DateNotice Of ActionDescription
6/14/2006 Approved Items 1 through 4 and 7 through 18 on the Consent Agenda. Item 5 was deferred in Council's afternoon session and Item 6 was pulled by Councilwoman Leary.
6/4/2006 Received By Clerk's Office
 
View Attachments 06-0370
FileTypeSizeDescription
Map - Big Bethel Road/Roberta Drive Map 0K Map - Big Bethel Road/Roberta Drive
Map - Big Bethel Road/Joynes Road Map 0K Map - Big Bethel Road/Joynes Road
 
Legislation Text 06-0370

 

City of Hampton, Virginia

Resolution

22 Lincoln Street

Hampton, VA 23669

www.hampton.gov

 

File Number: 06-0370

 

Enactment Number: -

 

Resolution Approving the Location and Major Design Features of the Big Bethel Road / Roberta Drive Intersection Improvements Project and the Big Bethel Road / Joynes Road Intersection Improvements Project. Engineering Services Project Numbers 04-001 and 05-007.

 

RESOLUTION

 

WHEREAS, a public hearing was conducted on May 10, 2006 in the City of Hampton by representatives of the City, after due and proper notice for the purposes of considering the proposed location and design of intersection improvements at Big Bethel Road/Roberta Drive (UPC #68099) and Big Bethel Road/Joynes Road (UPC #71455), at which meeting project plans and other pertinent information were made available for public inspection according to State requirements; and

 

WHEREAS, the project scopes include:

 

Big Bethel Road/Roberta Drive: mast arms/traffic signals, a raised median on the north side of the intersection, and median modifications on the south side of the intersection; and

 

Big Bethel Road/Joynes Road: a mast arms/traffic signals and curbing modifications, and

 

WHEREAS, all persons and parties in attendance were afforded full opportunity of participating in said public meeting; and

 

WHEREAS, representatives of the City of Hampton were present and participated in said meeting; and

 

WHEREAS, Council had previously requested the Virginia Department of Transportation to program these projects; and

 

WHEREAS, the Council considered all such matters.

 

NOW, THEREFORE, BE IT RESOLVED that the Council in the City of Hampton hereby approves the location and major design features of the Big Bethel Road/Roberta Drive Intersection Improvements project and the Big Bethel Road/Joynes Road Intersection Improvements project as presented at the public hearing.

 

Adopted at the regular meeting of the City Council of the City of Hampton, Virginia held on June 14, 2006.

 

 

 

Signed by ____________________________ Date _________________

Ross A. Kearney, II, Mayor

 

 

 

 

Attested by ____________________________ Date _________________

Katherine K. Glass

Clerk of the Council